Bruce A Restart Reactor VAULT MODIFICATIONS
Location
Tiverton, Ontario
Owner
Bruce Power
Jingoli personnel planned and managed projects for Bruce Power in the reactor vaults of Units 1 & 2 during the Bruce A Restart project. These projects were on the Critical Path immediately after reactor refueling, and were conducted around the clock in a Zone 3 Radiological Area using three-hour work crew jumps to minimize time of exposure.
The projects consisted of:
- Reversal of temporary modifications on the east and west reactor faces made during the retube of the Unit 1 and Unit 2 Calandrias
- Modification of the fueling machine bridge Y-drive
- Disconnection and removal of the temporary power supplies and fueling machine bridge Y-Drive modifications
- Installation of the X and Y-Drive power supplies, limit switches, and panels
- Modifications to the service and breathing air systems
- Removal of the vault bulkhead and the working platform at the reactor face
- Performing an extensive rebuild and reinstallation of the reactor area bridge and carriage
- Execution of the vault pressure test
- Decontamination and storage of all removed components