The project consisted of a data center expansion program in a live environment for a major multinational financial firm. The program involved several critical phases of white space expansion, mechanical, and electrical infrastructure upgrades. The ultimate goal was to deliver a flexible infrastructure capable of supporting high-density requirements in a Tier 3+ configuration.
- New 13.2 kv electrical service from the local utility.
- N+1 parallel redundant 7.5-megawatt generator plant.
- 3.5 megawatt UPS in a 2N configuration.
- Infrastructure upgrades to support 150 watts per square feet density.
- 900-ton chiller plant in an N+1 configuration.
- Complete upgrade of telecom infrastructure to support multiple carrier access.
- Diverse and redundant points of entry and distribution.
- Complete exterior and interior refurbishment.
![](/sites/default/files/styles/project_additional_imgs/public/project/DSC_0007.jpg?itok=LF0mwslp)
![](/sites/default/files/styles/project_additional_imgs/public/project/DSC_0033.jpg?itok=Ujip9RDo)
![](/sites/default/files/styles/project_additional_imgs/public/project/DSC_0050.jpg?itok=ded3JjUa)
![](/sites/default/files/styles/project_additional_imgs/public/project/DSC_0092.jpg?itok=KS5tUwS0)
![](/sites/default/files/styles/project_additional_imgs/public/project/DSC_0143.jpg?itok=OQiyl_s7)
![](/sites/default/files/styles/project_additional_imgs/public/project/DSC_0149.jpg?itok=5u-6xY_E)
![](/sites/default/files/styles/project_additional_imgs/public/project/DSC_0155.jpg?itok=RjaH985o)
![](/sites/default/files/styles/project_additional_imgs/public/project/DSC_00552.jpg?itok=1106GQt5)